By opening the furnace, we are going to have pig iron, our product. “In March next year, we are going to open the steel mill.
In June or July next year, we will have steel from Manhize.
Zimbabwe will no longer need to import.
We will have enough to meet the local demand,” he said.
Last year, the firm inked a deal with power utility, Zesa Holdings, to construct a 100 kilometre powerline linking the operation to the national grid.
This week, Xu said work on the powerline was still at preliminary stage. “The powerline is at early stage.
We have temporary power solutions, which can help us energise the plant,” he noted. “For our project expansion, definitely, we need to have a distribution line.
So we are working closely with Zesa to implement the project together. ” Reports early this year indicated that authorities had reached out to Mozambique’s Mphanda Nkuwa hydroelectric power project to secure exclusive power imports for the five million tonnes-a-year steel and ferrochrome operation.
In an interview with the Independent earlier this year, a Disco official said if the power import deals, which are being spearheaded by national power utility, Zesa Holdings, are successful, dedicated power would be routed from Mphanda Nkuwa hydroelectric power station in Mozambique’s Tete province exclusively for the project. “Zesa promised us that they will provide enough electricity,” Wilfred Motsi, project manager at Disco, said when asked how the project would be powered, given the electricity shortages confronting Zimbabwe. “We will get enough electricity to power the plant.
In the first phase, the plant will require 100MW, and at full throttle we will require a total of 800MW. ” The Mphanda Nkuwa power facility is on the Zambezi River, about 60 kilometres downstream of the existing Cahora Bassa Dam near Tete, which also occasionally exports power to Zimbabwe.
The firm will shell out about US$4,5 billion to complete the facility, which is expected to reach financial close at the end of next year, before commissioning in 2031, according to the African Development Bank, which became advisor last May. 🔗
” style=”color: #007bff;”>admin@allzimnews. com.
📖 Continue Reading
This is a preview of the full article. To read the complete story, click the button below to visit thestandard.
🔗 Read Full Article on thestandard